Violation Detail
Standard Cited: 19100106 B02 IV A Flammable liquids.
Inspection Nr: 1061259.015
Citation: 01001
Citation Type: Other
Abatement Date: 12/09/2015 2
Initial Penalty: $7,000.00
Current Penalty: $5,600.00
Issuance Date: 10/19/2015
Nr Instances: 1
Nr Exposed: 4
Related Event Code (REC): R
Gravity:
Report ID: 0523900
Contest Date:
Final Order: 11/03/2015
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 11/03/2015 | $5,600.00 | 12/09/2015 | Other | |
Penalty | Z: Issued | 10/19/2015 | $7,000.00 | 12/09/2015 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1910.106(b)(2)(iv)(a): Atmospheric storage tanks were not adequately vented to prevent the development of vacuum or pressure sufficient to distort the roof of a cone roof tank or exceeding the design pressure in the case of other atmospheric tanks, as a result of filling or emptying, and atmospheric temperature changes: (a) Oil Movements, Polymer Modified Asphalt Tank 113; On or about April 28, 2015 Calumet Superior, LLC. did not ensure the atmospheric tank had adequate venting to prevent over pressurization of the tank.