Violation Detail
Standard Cited: 19260404 F06 Wiring design and protection.
Inspection Nr: 1300048.015
Citation: 01001
Citation Type: Serious
Abatement Date: 3
Initial Penalty: $2,356.00
Current Penalty: $1,178.00
Issuance Date: 04/23/2018
Nr Instances: 1
Nr Exposed: 9
Related Event Code (REC):
Gravity: 5
Report ID: 0729700
Contest Date:
Final Order: 05/08/2018
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 05/08/2018 | $1,178.00 | Serious | ||
Penalty | Z: Issued | 04/23/2018 | $2,356.00 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1926.404(f)(6): The path to ground from circuits, equipment, or enclosures was not permanent and continuous: Employees engaged in charging the Skyjack #21436 scissor lift on the second floor of the job site near column post C6 were exposed to electrical hazards due to no ground pin on the charging cord plug end.