Violation Detail
Standard Cited: 19100124 J03
Inspection Nr: 1334039.015
Citation: 01001
Citation Type: Other
Abatement Date: 02/21/2019 2
Initial Penalty: $744.00
Current Penalty: $744.00
Issuance Date: 01/25/2019
Nr Instances: 1
Nr Exposed: 6
Related Event Code (REC):
Gravity:
Report ID: 0420600
Contest Date:
Final Order: 02/19/2019
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | Z: Issued | 01/25/2019 | $744.00 | 02/21/2019 | Other |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1910.124(j)(3): Periodic inspections of all dipping and coating equipment, including covers, drains, overflow piping, and electrical and fire-extinguishing systems were not conducted, and deficiencies were not promptly corrected: a) At the motor rewinding shop, employees used a varnish dip tank that contained a flammable hazardous chemical and no safety inspections for the dipping operation had been conducted. As observed on or about 07/31/2018.