Violation Detail
Standard Cited: 19100147 C04 I The control of hazardous energy (lockout/tagout).
Inspection Nr: 1367899.015
Citation: 01001
Citation Type: Other
Abatement Date: 05/13/2019 2
Initial Penalty: $13,260.00
Current Penalty: $13,260.00
Issuance Date: 05/01/2019
Nr Instances: 1
Nr Exposed: 1
Related Event Code (REC): A
Gravity:
Report ID: 0626000
Contest Date:
Final Order: 05/28/2019
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 05/28/2019 | $13,260.00 | 05/13/2019 | Other | |
Penalty | Z: Issued | 05/01/2019 | $13,260.00 | 05/13/2019 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1910.147(c)(4)(i): Procedures were not developed, documented and utilized for the control of potentially hazardous energy when employees were engaged in activities covered by this section: On or about December 20, 2018, maintenance activity was performed on a support leg of a perforator machine without a documented procedure to control the effect of gravitational energy.