Violation Detail
Standard Cited: 19100147 C04 I The control of hazardous energy (lockout/tagout).
Inspection Nr: 1501454.015
Citation: 01001
Citation Type: Serious
Abatement Date: 03/03/2021 2
Initial Penalty: $5,461.00
Current Penalty: $4,000.00
Issuance Date: 02/23/2021
Nr Instances: 1
Nr Exposed: 2
Related Event Code (REC): A
Gravity: 10
Report ID: 0111400
Contest Date:
Final Order: 03/18/2021
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 03/18/2021 | $4,000.00 | 03/03/2021 | Serious | |
Penalty | Z: Issued | 02/23/2021 | $5,461.00 | 03/03/2021 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1910.147(c)(4)(i): Procedures were not developed, documented and utilized for the control of potentially hazardous energy when employees were engaged in activities covered by this section: Location: 451 American Legion Hwy, Boston MA 02118 Employees were exposed to the hazards associated with the release of the unexpected energization or start up of the machine while conducting repairs on the Backers 3-TAL Powerscreen Machine where procedures were not utilized to prevent the accidental activation of the machine.