Standard Cited: 19100179 G05 III Overhead and gantry cranes.
This violation item has been deleted.
Inspection Nr: 1564857.015
Citation: 01001
Citation Type: Serious
Abatement Date: 01/11/2022 2
Initial Penalty: $9,753.00
Current Penalty: $0.00
Issuance Date: 12/14/2021
Nr Instances: 1
Nr Exposed: 1
Related Event Code (REC):
Gravity: 5
Report ID: 0729700
Contest Date:
Final Order: 01/10/2022
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 01/10/2022 | $0.00 | 01/11/2022 | Serious | |
Penalty | Z: Issued | 12/14/2021 | $9,753.00 | 01/11/2022 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1910.179(g)(5)(iii):Floor-operated crane(s) were not provided with a switch or circuit breaker of the enclosed type, with provision for locking in the open position, in the leads from the runway conductors: In the Packaging Area, employee(s) engaged in packing activities were exposed to a struck by hazard in that the floor operated crane was hard wired into a junction box without the use of an electrical panel disconnect.