Standard Cited: 19100269 A03 I C Electric Power Generation, Transmission, and Distribution.
This violation item has been deleted.
Inspection Nr: 1134884.015
Citation: 01001A
Citation Type: Serious
Abatement Date: 10/20/2016
Initial Penalty: $12,471.00
Current Penalty: $0.00
Issuance Date: 09/01/2016
Nr Instances: 1
Nr Exposed: 2
Related Event Code (REC):
Gravity: 10
Report ID: 0418200
Contest Date:
Final Order: 09/27/2016
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 09/27/2016 | $0.00 | 10/20/2016 | Serious | |
Penalty | Z: Issued | 09/01/2016 | $12,471.00 | 10/20/2016 | Serious |
Text For Citation: 01 Item/Group: 001A Hazard:
29 CFR 1910.269(a)(3)(i)(C): Information about the design and operation of the host employer's installation that the contract employer needs to make the assessments required by this section; a. Unit 3, Cooling Tower - The host employer (Georgia Power) did not provide the contract employer (Fluor) electrical circuit drawings or other relevant information needed for determining whether conductors to be removed from Cooling Tower conduit were disconnected and de-energized. The failure to provide adequate circuitry information prevented the transfer of needed information such as the nominal voltage on lines and equipment to be removed during the Fluor demolition process.