Violation Detail
Standard Cited: 19260451 B01 General requirements.
This violation item has been deleted.
Inspection Nr: 1463209.015
Citation: 01001A
Citation Type: Serious
Abatement Date: 07/23/2020 5
Initial Penalty: $12,145.00
Current Penalty: $0.00
Issuance Date: 06/24/2020
Nr Instances: 1
Nr Exposed: 2
Related Event Code (REC): A
Gravity: 10
Report ID: 0636900
Contest Date: 07/21/2020
Final Order: 03/04/2022
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 03/04/2022 | $0.00 | 07/23/2020 | Serious | |
Penalty | C: Contested | 08/10/2020 | $12,145.00 | 07/23/2020 | Serious | |
Penalty | Z: Issued | 06/24/2020 | $12,145.00 | 07/23/2020 | Serious |
Text For Citation: 01 Item/Group: 001A Hazard:
29 CFR 1926.451(b)(1): Each platform on all working levels of scaffolds was not fully planked or decked between the front uprights and the guardrail supports as specified in paragraphs 1926.451(b)(1)(i)-(ii). On or about February 13, 2020, at the New Sherman High School Project, employees directed to perform masonry activities on welded framed scaffold platforms that were not fully planked were exposed to an approximately18 feet fall hazard.