Violation Detail
Standard Cited: 19260752 D Site layout, site-specific erection plan and construction sequence.
Inspection Nr: 1343350.015
Citation: 01001B
Citation Type: Serious
Abatement Date: 02/28/2019 4
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 02/22/2019
Nr Instances: 1
Nr Exposed: 3
Related Event Code (REC): A
Gravity: 10
Report ID: 0830300
Contest Date:
Final Order: 03/15/2019
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 03/15/2019 | $0.00 | 02/28/2019 | Serious | |
Penalty | Z: Issued | 02/22/2019 | $0.00 | 02/28/2019 | Serious |
Text For Citation: 01 Item/Group: 001B Hazard:
29 CFR 1926.752(d): Pre-planning of overhead hoisting operations. Hoisting operations in steel erection were not pre-planned to ensure that the requirements of �� 1926.753(d) were met: (a) On August 25th, 2018 and at time prior the employees were exposed to struck-by hazards where the employer failed to pre-plan all hoisting operations before commencing steel erection work in the vicinity of 72nd Avenue NW & 38th Street NW in Parshall, North Dakota.