Violation Detail
Standard Cited: 19100421 D Pre-dive procedures.
Inspection Nr: 1380591.015
Citation: 01001B
Citation Type: Serious
Abatement Date: 09/05/2019 2
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 08/16/2019
Nr Instances: 1
Nr Exposed: 3
Related Event Code (REC): A
Gravity: 1
Report ID: 0625400
Contest Date:
Final Order: 09/17/2019
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 09/17/2019 | $0.00 | 09/05/2019 | Serious | |
Penalty | Z: Issued | 08/16/2019 | $0.00 | 09/05/2019 | Serious |
Text For Citation: 01 Item/Group: 001B Hazard:
29 CFR 1910.421(d): Assessments made during planning of dive operations did not include all safety and health aspects specified in 29 CFR 1910.421(d)(1) through 29 CFR 1910.421(d)(9): 29 CFR 1926.605(e): Commercial diving operations were not in accordance with subpart T of part 1910, 1910.401-1910.441, in that 29 CFR 1910.421(d) was violated: On or about February 21, 2019, a SCUBA diver and attendant were retrieving a submerged irrigation pump approximately 50 feet deep at the bottom of a lake without the employer performing an assessment of; reserve gas supply and emergency procedures, exposing employees at the dive site to the hazards associated with SCUBA diving.