Violation Detail
Standard Cited: 19260404 F06 Wiring design and protection.
Inspection Nr: 1245706.015
Citation: 01002
Citation Type: Serious
Abatement Date: 05/09/2018 2
Initial Penalty: $12,675.00
Current Penalty: $8,000.00
Issuance Date: 11/17/2017
Nr Instances: 2
Nr Exposed: 2
Related Event Code (REC): A
Gravity: 10
Report ID: 0524200
Contest Date: 12/13/2017
Final Order: 04/09/2018
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 04/09/2018 | $8,000.00 | 05/09/2018 | Serious | |
Penalty | C: Contested | 12/19/2017 | $12,675.00 | 11/24/2017 | Serious | |
Penalty | Z: Issued | 11/17/2017 | $12,675.00 | 11/24/2017 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1926.404(f)(6): The path to ground from circuits, equipment, or enclosures was not permanent and continuous: a) On or about July 7, 2017, employees were using an electrical power tool that was missing its ground pin. b) On or about July 7, 2017, employees were using an electrical power tool that was plugged into an extension cord that was missing its ground pin. In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET), and in addition, documentation demonstrating that abatement is complete must be included with your certification. This documentation may include, but is not limited to, evidence of the purchase or repair of the equipment, photographic or video evidence of abatement, or other written records.