Violation Detail
Standard Cited: 19260451 E01 General requirements.
Inspection Nr: 1248336.015
Citation: 01002
Citation Type: Serious
Abatement Date: 01/22/2018 2
Initial Penalty: $2,956.00
Current Penalty: $2,565.00
Issuance Date: 01/11/2018
Nr Instances: 1
Nr Exposed: 3
Related Event Code (REC):
Gravity: 5
Report ID: 0215000
Contest Date: 01/26/2018
Final Order: 06/22/2018
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 06/22/2018 | $2,565.00 | 01/22/2018 | Serious | |
Penalty | C: Contested | 02/07/2018 | $2,956.00 | 01/22/2018 | Serious | |
Penalty | Z: Issued | 01/11/2018 | $2,956.00 | 01/22/2018 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1926.451(e)(1): When scaffold platforms were more than 2 feet (0.6 m) above or below a point of access, portable ladders, hook-on ladders, attachable ladders, stair towers (scaffold stairways/towers), stairway-type ladders (such as ladder stands), ramps, walkways, integral prefabricated scaffold access, or direct access from other scaffold, structure, personnel hoist, or similar surface was not used. Location: a) Supported scaffold on the southeast side of the first floor of the jobsite: On or about 07/12/17, employees were not provided a safe access to the first tier platform of a 1-tier-high supported scaffold.