Violation Detail
Standard Cited: 19100147 C06 I The control of hazardous energy (lockout/tagout).
Inspection Nr: 1045930.015
Citation: 01002C
Citation Type: Serious
Abatement Date: 11/15/2015 2
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 05/15/2015
Nr Instances: 1
Nr Exposed: 3
Related Event Code (REC):
Gravity: 10
Report ID: 0213600
Contest Date: 06/11/2015
Final Order: 01/11/2016
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | J: ALJ Decision | 01/11/2016 | $0.00 | 11/15/2015 | Serious | |
Penalty | C: Contested | 06/12/2015 | $0.00 | 06/19/2015 | Serious | |
Penalty | Z: Issued | 05/15/2015 | $0.00 | 06/19/2015 | Serious |
Text For Citation: 01 Item/Group: 002C Hazard:
29 CFR 1910.147(c)(6)(i): The employer did not conduct an annual or more frequent inspection of the energy control procedure to ensure that the procedure and requirements of this standard were followed: a) Facility - On or about 3/11/15, employees repair, service and maintain equipment such as the HD/VTS Trim Press (480V/60Hz/3 phase; 110 psi). The employer did not conduct an annual or more frequent inspection of the energy control procedure to ensure that the procedure and requirements of this standard were followed. ABATEMENT DOCUMENTATION REQUIRED