Violation Detail
Standard Cited: 19100134 F02 Respiratory Protection.
Inspection Nr: 1279307.015
Citation: 01002C
Citation Type: Serious
Abatement Date: 06/15/2018 5
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 03/28/2018
Nr Instances: 1
Nr Exposed: 4
Related Event Code (REC):
Gravity: 5
Report ID: 0317900
Contest Date:
Final Order: 05/09/2018
Emphasis:
Substance: 1591
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 05/09/2018 | $0.00 | 06/15/2018 | Serious | |
Penalty | Z: Issued | 03/28/2018 | $0.00 | 04/17/2018 | Serious |
Text For Citation: 01 Item/Group: 002C Hazard:
29 CFR 1910.134(f)(2): Employee(s) using tight-fitting facepiece respirators were not fit tested prior to initial use of the respirator: (Construction Reference 1926.103) a) Building L, Rooms 218 through 221: Employees were required to wear 3M N95 respirators while manually scraping lead paint from the exterior walls and beams and the employer did not provide the employees with a fit test, on or about November 28, 2017. Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states that employees and their representatives were informed of this abatement.