Violation Detail
Standard Cited: 19100119 D03 I B Process safety management of highly hazardous chemicals.
Inspection Nr: 1021723.015
Citation: 01003
Citation Type: Serious
Abatement Date: 09/08/2015 2
Initial Penalty: $6,300.00
Current Penalty: $4,410.00
Issuance Date: 07/22/2015
Nr Instances: 1
Nr Exposed: 4
Related Event Code (REC):
Gravity: 10
Report ID: 0214200
Contest Date:
Final Order: 07/31/2015
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 07/31/2015 | $4,410.00 | 09/08/2015 | Serious | |
Penalty | Z: Issued | 07/22/2015 | $6,300.00 | 09/08/2015 | Serious |
Text For Citation: 01 Item/Group: 003 Hazard:
29 CFR 1910.119(d)(3)(i)(B): Process safety information pertaining to the equipment in the process did not include the piping and instrumentation diagrams (P&IDs): a) Compounding Area The employer did not have the required P&IDs for the process equipment. Employees manufactured perfumes/colognes using denatured alcohol, a flammable liquid. Processes occurring during the inspection included, but were not limited to, pumping and mixing/agitation of 14,000lbs of flammable liquids. Violation occurred on or about 1/22/2015.