Violation Detail
Standard Cited: 19100178 G02 Powered industrial trucks.
Inspection Nr: 1148208.015
Citation: 01003
Citation Type: Serious
Abatement Date: 11/23/2016 2
Initial Penalty: $4,988.00
Current Penalty: $2,631.00
Issuance Date: 10/27/2016
Nr Instances: 1
Nr Exposed: 1
Related Event Code (REC):
Gravity: 5
Report ID: 0213900
Contest Date: 11/21/2016
Final Order: 05/19/2017
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | J: ALJ Decision | 05/19/2017 | $2,631.00 | 11/23/2016 | Serious | |
Penalty | C: Contested | 12/13/2016 | $4,988.00 | 11/23/2016 | Serious | |
Penalty | Z: Issued | 10/27/2016 | $4,988.00 | 11/23/2016 | Serious |
Text For Citation: 01 Item/Group: 003 Hazard:
29 CFR 1910.178(g)(2): Battery charging apparatus for industrial trucks located in battery changing and charging installation was not protected from damage by trucks: a) Baker Boys LLC DBA Formica Bros. Bakery - Forklift charging area: The facility did not protect the battery charging apparatuses from damage. The charging cables on a Hobart / Accu-charger, Model #725C3-24, Serial# N6396A had damaged cords and the exposed copper conduit was covered with masking tape, observed on or about 05/04/4016.