Violation Detail
Standard Cited: 19261437 N05
Inspection Nr: 1366166.015
Citation: 01003
Citation Type: Serious
Abatement Date: 3
Initial Penalty: $8,354.00
Current Penalty: $4,177.00
Issuance Date: 06/07/2019
Nr Instances: 1
Nr Exposed: 4
Related Event Code (REC):
Gravity: 10
Report ID: 0420600
Contest Date:
Final Order: 06/27/2019
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 06/27/2019 | $4,177.00 | Serious | ||
Penalty | Z: Issued | 06/07/2019 | $8,354.00 | Serious |
Text For Citation: 01 Item/Group: 003 Hazard:
29 CFR 1926.1437(n)(5): The physical attachment, corralling, rail system, or centerline cable system did not meet the requirements of options 1 through 4 of this section, or meet the requirements of paragraph (n)(5)(v) of this section: a) At the "A" Dock of the Twin Dolphin Marina, on or about December 13, 2018, the crawler crane on a barge used for a pile driving operation was not physically attached to the barge, nor was any other system in use to prevent the crane from shifting.