Standard Cited: 19100106 I03 II Flammable liquids.
This violation item has been deleted.
Inspection Nr: 315723312
Citation: 01003
Citation Type: Serious
Abatement Date: 06/04/2012
Initial Penalty: $7,000.00
Current Penalty:
Issuance Date: 05/01/2012
Nr Instances: 1
Nr Exposed: 40
Related Event Code (REC): R
Gravity: 10
Report ID: 0626700
Contest Date: 05/25/2012
Final Order: 02/15/2013
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | J: ALJ Decision | 02/15/2013 | 06/04/2012 | Serious | ||
Penalty | Z: Issued | 05/01/2012 | $7,000.00 | 06/04/2012 | Serious |
Text For Citation: 01 Item/Group: 003 Hazard: CHEMNEP
29 CFR 1910.106(i)(3)(ii): Unfired vessels were not constructed in accordance with the Code for Unfired Pressure Vessels, Section VIII of the ASME Boiler and Pressure Vessel Code-1968: a)This condtion was observed at the, at E. I. du Pont de Nemours and Company, in Beaumont, TX, in the Aniline Unit where the employer did not ensure that the Purge Column was constructed in accordance with Section VIII of the ASME Boiler and Pressure Vessel Code, when the employer failed to ensure RV-J-0111 relieved to a safe location, exposing employees to a toxic material.