Violation Detail
Standard Cited: 19100036 B01 Design and construction requirements for exit routes.
Inspection Nr: 1044015.015
Citation: 01003A
Citation Type: Serious
Abatement Date: 06/15/2015 2
Initial Penalty: $4,900.00
Current Penalty: $3,185.00
Issuance Date: 04/27/2015
Nr Instances: 2
Nr Exposed: 10
Related Event Code (REC):
Gravity: 10
Report ID: 0215800
Contest Date:
Final Order: 05/18/2015
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 05/18/2015 | $3,185.00 | 06/15/2015 | Serious | |
Penalty | Z: Issued | 04/27/2015 | $4,900.00 | 05/30/2015 | Serious |
Text For Citation: 01 Item/Group: 003A Hazard:
29 CFR 1910.36(b)(1): At least two exit routes were not available in the workplace to permit prompt evacuation of employees and other building occupants during an emergency. The exit routes must be located as far away as practical from each other so that if one exit route is blocked by fire or smoke, employees can evacuate using the second exit route: a) Warehouse #5, on or about 3/3/15: There was only one means of egress from the building. b) Warehouse #2, on or about 3/3/15: There was only one means of egress from three storage bays at the east end of building and pipe shed. Abatement documentation must be submitted for these items.