Violation Detail
Standard Cited: 19100147 D04 I The control of hazardous energy (lockout/tagout).
Inspection Nr: 1553596.015
Citation: 01003B
Citation Type: Serious
Abatement Date: 04/07/2022 2
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 03/10/2022
Nr Instances: 4
Nr Exposed: 4
Related Event Code (REC): A
Gravity: 10
Report ID: 0523300
Contest Date:
Final Order: 04/04/2022
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 04/04/2022 | $0.00 | 04/07/2022 | Serious | |
Penalty | Z: Issued | 03/10/2022 | $0.00 | 04/07/2022 | Serious |
Text For Citation: 01 Item/Group: 003B Hazard:
29 CFR 1910.147(d)(4)(i):Lockout or tagout devices were not affixed to each energy isolating device by authorized employees: Maintenance and laser operator did not affix energy control devices to Trumpf laser material handling lifts: a. On or about September 17, 2021, a maintenance employee entered the material handling area to adjust slat bolts on index table. b. On or about September 17, 2021, and October 19, 2021, laser operators entered the material handling area to clean the index table slats. c. On or about October 01, 2021, to October 08, 2021, laser operators entered the material handling area to replace index table slats. d. On or about September 17, 2021, laser operators entered the material handling area to perform cleaning activities.