Violation Detail
Standard Cited: 19100303 C03 I General.
Inspection Nr: 1525767.015
Citation: 01003C
Citation Type: Serious
Abatement Date: 08/11/2021 2
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 07/16/2021
Nr Instances: 1
Nr Exposed: 2
Related Event Code (REC): A
Gravity: 10
Report ID: 0522300
Contest Date:
Final Order: 08/12/2021
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 08/12/2021 | $0.00 | 08/11/2021 | Serious | |
Penalty | Z: Issued | 07/16/2021 | $0.00 | 08/11/2021 | Serious |
Text For Citation: 01 Item/Group: 003C Hazard:
29 CFR 1910.303(c)(3)(i):Conductors shall be spliced or joined with splicing devices identified for the use or by brazing, welding, or soldering with a fusible metal or alloy. Soldered splices shall first be spliced or joined to be mechanically and electrically secure without solder and then soldered. All splices and joints and the free ends of conductors shall be covered with an insulation equivalent to that of the conductors or with an insulating device identified for the purpose. On or about April 12, 2021, the employer did not ensure the conductors of a Miller, Millermatic 350P portable welder machine's electrical power cable were spliced and jointed with solder and covered with an insulation equivalent to that of the conductors or the cable.