Standard Cited: 19100119 E01 Process safety management of highly hazardous chemicals.
This violation item has been deleted.
Inspection Nr: 315723312
Citation: 01004B
Citation Type: Serious
Abatement Date: 06/04/2012
Initial Penalty:
Current Penalty:
Issuance Date: 05/01/2012
Nr Instances: 1
Nr Exposed: 40
Related Event Code (REC): R
Gravity: 10
Report ID: 0626700
Contest Date: 05/25/2012
Final Order: 02/15/2013
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | J: ALJ Decision | 02/15/2013 | 06/04/2012 | Serious | ||
Penalty | Z: Issued | 05/01/2012 | 06/04/2012 | Serious |
Text For Citation: 01 Item/Group: 004B Hazard: CHEMNEP
29 CFR 1910.119(e)(1): The process hazard analysis was not appropriate to the complexity of the process and did not identify, evaluate, and address the control of the hazards involved in the process. a)This condition was observed at the E. I. du Pont de Nemours and Company, in Beaumont, TX, where the employer did not ensure that the Process Hazard Analysis (PHA) was appropriate to the complexity of the process, and that the PHA identified, evaluated and addressed control of the hazard involved in the process when the employer failed to ensure that RV-J-0111 relieved to a safe location, therefore exposing employees to an atmosheric release of toxic material.c