Violation Detail
Standard Cited: 19101200 E01 Hazard Communication.
Inspection Nr: 1279307.015
Citation: 01004C
Citation Type: Serious
Abatement Date: 06/15/2018 5
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 03/28/2018
Nr Instances: 1
Nr Exposed: 4
Related Event Code (REC): C
Gravity: 5
Report ID: 0317900
Contest Date:
Final Order: 05/09/2018
Emphasis:
Substance: 1591
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 05/09/2018 | $0.00 | 06/15/2018 | Serious | |
Penalty | Z: Issued | 03/28/2018 | $0.00 | 04/12/2018 | Serious |
Text For Citation: 01 Item/Group: 004C Hazard:
29 CFR 1910.1200(e)(1): The employer did not develop, implement, and/or maintain at the workplace a written hazard communication program which describes how the criteria specified in 29 CFR 1910.1200(f), (g), and (h) will be met: (Construction Reference: 1926.59): a) Building L, Rooms 218 through 221: Employees were manually scraping lead paint from the exterior walls and beams and using Sherwin Williams ProBlock Primer to seal the walls. The employer did not have a written hazard communication program, on or about November 28, 2017. Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states that employees and their representatives were informed of this abatement.