Violation Detail
Standard Cited: 19100179 J03 Overhead and gantry cranes.
Inspection Nr: 961334.015
Citation: 01007
Citation Type: Serious
Abatement Date: 08/30/2014 2
Initial Penalty: $5,000.00
Current Penalty: $3,500.00
Issuance Date: 07/30/2014
Nr Instances: 1
Nr Exposed: 20
Related Event Code (REC):
Gravity: 5
Report ID: 0213600
Contest Date:
Final Order: 08/21/2014
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 08/21/2014 | $3,500.00 | 08/30/2014 | Serious | |
Penalty | Z: Issued | 07/30/2014 | $5,000.00 | 08/30/2014 | Serious |
Text For Citation: 01 Item/Group: 007 Hazard:
29 CFR 1910.179(j)(3): A complete periodic inspection of crane(s) had not been conducted in the past 12 months: a) On or about 03/05/2014, throughout the plant, the last inspections of overhead cranes such as, but not limited to: 2 ton powered trolley weld shop outside steel storage, 1 ton beam trolley electrical shop, 2 ton manual trolley round house, 2 ton manual bridge trolley machine shop, 3 ton beam trolley A&D belts coke handling, 1 ton beam trolley outside #1DD coke handling, 1 ton beam trolley over #1 DD coke handling, 1 ton beam trolley over # 3DD coke handling, oven door room stationary crane battery, 2 ton beam trolley top of coal handling and 1 ton beam trolley breeze crusher coal handling were conducted on 02/20/2009. ABATEMENT DOCUMENTATION REQUIRED