Standard Cited: 19100147 D03 The control of hazardous energy (lockout/tagout).
Inspection Nr: 965405.015
Citation: 01008A
Citation Type: Serious
Abatement Date: 01/30/2015 2
Initial Penalty: $7,000.00
Current Penalty: $7,000.00
Issuance Date: 09/22/2014
Nr Instances: 1
Nr Exposed: 1
Related Event Code (REC): A
Gravity: 10
Report ID: 0522000
Contest Date:
Final Order: 10/20/2014
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 10/20/2014 | $7,000.00 | 01/30/2015 | Serious | |
Penalty | Z: Issued | 09/22/2014 | $7,000.00 | 10/02/2014 | Serious |
Text For Citation: 01 Item/Group: 008A Hazard:
29 CFR 1910.147(d)(3): Machine or equipment isolation. All energy isolating devices that are needed to control the energy to the machine or equipment shall be physically located and operated in such a manner as to isolate the machine or equipment from the energy source(s). The employer failed to develop adequate procedures for the elimination, isolation, restraint and relief of pneumatic energy sources to the outer metal door of the quench tank chamber of the AFE-6 Casemaster furnance during the insertion of an extended wrench into the quench tank chamber of the furnance to adjust the quench tank elevator.