Violation Detail
Standard Cited: 19100269 D02 V Electric Power Generation, Transmission, and Distribution.
This violation item has been deleted.
Inspection Nr: 900009.015
Citation: 01010
Citation Type: Serious
Abatement Date: 10/24/2013
Initial Penalty: $7,000.00
Current Penalty: $0.00
Issuance Date: 09/24/2013
Nr Instances: 1
Nr Exposed: 8
Related Event Code (REC):
Gravity: 10
Report ID: 0418200
Contest Date: 11/04/2013
Final Order: 12/05/2014
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 12/05/2014 | $0.00 | 10/24/2013 | Serious | |
Penalty | C: Contested | 12/30/2013 | $7,000.00 | 10/24/2013 | Serious | |
Penalty | Z: Issued | 09/24/2013 | $7,000.00 | 10/24/2013 | Serious |
Text For Citation: 01 Item/Group: 010 Hazard:
29 CFR 1910.269(d)(2)(v): The employer shall conduct a periodic inspection of the energy control procedure at least annually to ensure that the procedure and the provisions of paragraph (d) of this section are being followed. a. Unit 2 - Georgia Powers maintenance clearance procedure inspections did not ensure that all maintenance procedures that addressed the unexpected energization, startup or release of stored energy, were documented and adequate for controlling and rendered inoperative all hazardous energy sources.