Violation Detail
Standard Cited: 19100184 E03 I Slings.
Inspection Nr: 961334.015
Citation: 01010
Citation Type: Serious
Abatement Date: 08/30/2014 2
Initial Penalty: $5,000.00
Current Penalty: $3,500.00
Issuance Date: 07/30/2014
Nr Instances: 1
Nr Exposed: 20
Related Event Code (REC):
Gravity: 5
Report ID: 0213600
Contest Date:
Final Order: 08/21/2014
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 08/21/2014 | $3,500.00 | 08/30/2014 | Serious | |
Penalty | Z: Issued | 07/30/2014 | $5,000.00 | 08/30/2014 | Serious |
Text For Citation: 01 Item/Group: 010 Hazard:
29 CFR 1910.184(e)(3)(i): A thorough periodic inspection of alloy steel chain slings was not made on a regular basis and/or were done at intervals greater than once every 12 months: a) On or 03/05/14, throughout the plant, the last inspections of chains of overhead cranes such as, but not limited to: 2 ton powered trolley weld shop outside steel storage, 1 ton beam trolley electrical shop, 1 ton beam trolley outside #1 DD, 1 ton beam trolley over # 3DD and 1 ton beam trolley breeze crusher coal handling were conducted on 02/20/2009. ABATEMENT DOCUMENTATION REQUIRED