Violation Detail
Standard Cited: 19100269 D02 V E Electric Power Generation, Transmission, and Distribution.
Inspection Nr: 900009.015
Citation: 01011
Citation Type: Serious
Abatement Date: 10/24/2013 2
Initial Penalty: $7,000.00
Current Penalty: $7,000.00
Issuance Date: 09/24/2013
Nr Instances: 1
Nr Exposed: 9
Related Event Code (REC):
Gravity: 10
Report ID: 0418200
Contest Date: 11/04/2013
Final Order: 12/05/2014
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 12/05/2014 | $7,000.00 | 10/24/2013 | Serious | |
Penalty | C: Contested | 12/30/2013 | $7,000.00 | 10/24/2013 | Serious | |
Penalty | Z: Issued | 09/24/2013 | $7,000.00 | 10/24/2013 | Serious |
Text For Citation: 01 Item/Group: 011 Hazard:
29 CFR 1910.269(d)(2)(v)[E]: The periodic inspection certification of the energy control procedures did not contain the required documentation to identify the machine or equipment on which the energy control procedure was being used, the date of the inspection, the employees included in the inspection, and the person performing the inspection. a. Unit 2 - Georgia Power's annual audit reports did not identify the machines inspected or authorized employees who were interviewed during the audit. Georgia Power also, when conducting annual audits, did not identify and review the more critical clearance procedures, by unit, to be reviewed on an annual basis, while providing for other less critical clearance procedures to be reviewed on a random basis annually.