Violation Detail
Standard Cited: 19100305 B01 I Wiring methods, components, and equipment for general use.
This violation item has been deleted.
Inspection Nr: 1126756.015
Citation: 01011C
Citation Type: Serious
Abatement Date: 3
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 07/15/2016
Nr Instances: 1
Nr Exposed: 4
Related Event Code (REC):
Gravity: 10
Report ID: 0830600
Contest Date:
Final Order: 08/04/2016
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 08/04/2016 | $0.00 | Serious | ||
Penalty | Z: Issued | 07/15/2016 | $0.00 | Serious |
Text For Citation: 01 Item/Group: 011C Hazard:
29 CFR 1910.305(b)(1)(i): Conductors entering cutout boxes, cabinets, or fittings were not protected from abrasions: a) South rail dock crane: On or about March 4, 2016, and at times prior, crane wiring and equipment did not comply with Subpart S per 1910.179(g)(1)(i), in that workers were exposed to injuries related to electrical fires, shock, and electrocution where the crane cab heater cord entered a panel with no protection from the sharp edges of the opening. Abatement Note: Employer completed abatement during inspection.