Violation Detail
Standard Cited: 19100269 D06 II Electric Power Generation, Transmission, and Distribution.
Inspection Nr: 900009.015
Citation: 01013
Citation Type: Serious
Abatement Date: 10/24/2013 2
Initial Penalty: $7,000.00
Current Penalty: $7,000.00
Issuance Date: 09/24/2013
Nr Instances: 1
Nr Exposed: 9
Related Event Code (REC):
Gravity: 10
Report ID: 0418200
Contest Date: 11/04/2013
Final Order: 12/05/2014
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 12/05/2014 | $7,000.00 | 10/24/2013 | Serious | |
Penalty | C: Contested | 12/30/2013 | $7,000.00 | 10/24/2013 | Serious | |
Penalty | Z: Issued | 09/24/2013 | $7,000.00 | 10/24/2013 | Serious |
Text For Citation: 01 Item/Group: 013 Hazard:
29 CFR 1910.269(d)(6)(ii): The machine or equipment was not turned off or shut down using the procedures established for the machine or equipment: a. Unit 2 - On or about April 2-4, 2013, when the Unit 2 generator was being purged, all sources of hazardous energy were not isolated and rendered safe by the use of a maintenance clearance (tag out procedure) specifically established for that purpose.