Violation Detail
Standard Cited: 19100305 G02 III Wiring methods, components, and equipment for general use.
Inspection Nr: 1118903.015
Citation: 01017
Citation Type: Serious
Abatement Date: 06/25/2016 2
Initial Penalty: $2,800.00
Current Penalty: $1,000.00
Issuance Date: 06/24/2016
Nr Instances: 2
Nr Exposed: 2
Related Event Code (REC):
Gravity: 5
Report ID: 0625400
Contest Date:
Final Order: 09/29/2016
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 09/29/2016 | $1,000.00 | 06/25/2016 | Serious | |
Penalty | Z: Issued | 06/24/2016 | $2,800.00 | 06/25/2016 | Serious |
Text For Citation: 01 Item/Group: 017 Hazard:
29 CFR 1910.305(g)(2)(iii): Flexible cords were not connected to devices and fittings so that tension would not be transmitted to joints or terminal screws: a) On or about January 11, 2016, in the plastic department, at the Delta band saw, the employer failed to ensure the internal conductors were not pulled out at the strain relief area. Employees exposed to the hazard of an electrical shock. b) On or about January 11, 2016, in the assembly department, the Makita circular saw was plugged into an extension cord that had the internal conductors pulled out at the strain relief area. Employees exposed to the hazard of an electrical shock.