Violation Detail
Standard Cited: 19100253 B02 IV Oxygen-fuel gas welding and cutting.
Inspection Nr: 1356616.015
Citation: 01018
Citation Type: Serious
Abatement Date: 05/13/2019 2
Initial Penalty: $7,577.00
Current Penalty: $7,577.00
Issuance Date: 04/17/2019
Nr Instances: 1
Nr Exposed: 4
Related Event Code (REC):
Gravity: 5
Report ID: 0830100
Contest Date:
Final Order: 05/14/2019
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 05/14/2019 | $7,577.00 | 05/13/2019 | Serious | |
Penalty | Z: Issued | 04/17/2019 | $7,577.00 | 05/13/2019 | Serious |
Text For Citation: 01 Item/Group: 018 Hazard:
29 CFR 1910.253(b)(2)(iv): Valve protection caps, where cylinders were designed to accept caps, were not always in place, hand-tight, except when cylinders were in use or connected for use: a) Nelcon Asphalt Plant: On or about October 29, 2018 and at times prior, employees were exposed to explosion and secondary fire hazards from an uncapped acetylene tank stored outside of the maintenance trailer.