Violation Detail
Standard Cited: 19030019 C01 Abatement verification.
Inspection Nr: 1327252.015
Citation: 03001
Citation Type: Other
Abatement Date: 03/18/2019 7
Initial Penalty: $425.00
Current Penalty: $425.00
Issuance Date: 02/12/2019
Nr Instances: 1
Nr Exposed: 1
Related Event Code (REC):
Gravity:
Report ID: 0524200
Contest Date:
Final Order: 03/14/2019
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | Z: Issued | 02/12/2019 | $425.00 | 03/18/2019 | Other |
Text For Citation: 03 Item/Group: 001 Hazard:
29 CFR 1903.19(c)(1): The employer did not certify to OSHA, within 10 calendar days after the abatement date, that the cited violation had been abated: DB Custom Carpentry LLC., failed to certify to OSHA within 10 calendar days after the abatement date that each of the following cited violations had been corrected: Citation Number Item Number Abatement Date 01 01 12/21/2018 01 02 12/03/2018 02 01 12/03/2018 In accordance with 29 CFR 1903.19(c), abatement certification is required for this violation (using the CERTIFICATION OF THE CORRECTIVE ACTION WORKSHEET).