Standard Cited: 19100036 D01 Design and construction requirements for exit routes.
Inspection Nr: 77120.015
Citation: 03003
Citation Type: Other
Abatement Date: 3
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 12/05/2011
Nr Instances: 1
Nr Exposed: 70
Related Event Code (REC):
Gravity:
Report ID: 0524200
Contest Date: 12/27/2011
Final Order: 08/15/2012
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 08/15/2012 | $0.00 | Other | ||
Penalty | C: Contested | 01/03/2012 | $0.00 | Other | ||
Penalty | Z: Issued | 12/05/2011 | $0.00 | Other |
Text For Citation: 03 Item/Group: 003 Hazard:
29 CFR 1910.36(d)(1): Employee(s) were not able to open an exit route door from the inside at all times without keys, tools, or special knowledge: a) The exit door next to the Mechanic Shop near Bay#25 was locked by a key from the inside.