Violation Detail
Standard Cited: 19100303 B08 I General.
Inspection Nr: 1058109.015
Citation: 03006
Citation Type: Other
Abatement Date: 11/30/2015 3
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 10/08/2015
Nr Instances: 6
Nr Exposed: 1
Related Event Code (REC):
Gravity:
Report ID: 0111100
Contest Date:
Final Order: 11/02/2015
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 11/02/2015 | $0.00 | 11/30/2015 | Other | |
Penalty | Z: Issued | 10/08/2015 | $0.00 | Other |
Text For Citation: 03 Item/Group: 006 Hazard:
29 CFR 1910.303(b)(8)(i): Electrical equipment was not firmly secured to the surface on which it was mounted. Electrical equipment was not firmly secured to the surface on which it was mounted in the following instances: a) #8 Paper Machine - The three screws used to secure the panel cover to Lighting Panel #2, 10-MPP-2, were missing. b) #7 & 8 DE Mezzanine Process Power Panel - The two screws used to secure the panel cover to power panel were missing. c) Mill Stores Basement - The 120/208 volt Bond Garage Power Panel is missing two of six screws that were used to secure the panel cover. d) Bond Kitchen - Three armored cables were tie wrapped together in a bundle. e) Bond Kitchen - Armored cables along a horizontal beam were not adequately secured f) Pump 707 Area - The support brackets for the cable tray containing energized cables were detached from the tank surface.