Violation Detail
Standard Cited: 19260651 H01 Specific Excavation Requirements.
Inspection Nr: 1404729.015
Citation: 01002
Citation Type: Serious
Abatement Date: 3
Initial Penalty: $9,282.00
Current Penalty: $8,619.00
Issuance Date: 08/13/2019
Nr Instances: 1
Nr Exposed: 1
Related Event Code (REC):
Gravity: 10
Report ID: 0729300
Contest Date:
Final Order: 09/05/2019
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 09/05/2019 | $8,619.00 | Serious | ||
Penalty | Z: Issued | 08/13/2019 | $9,282.00 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1926.651(h)(1): Employees were working in an excavation in which there was accumulated water or excavations in which water was accumulating, and adequate precautions had not been taken to protect employees against the hazards posed by water accumulation: On or about 5/23/2019, employees of Lehman Construction LLC were installing a 24 inch storm pipe near the intersection of West Pearce Boulevard and Goodfellow Road, Wentzville, MO. Water was allowed to accumulate in the trench to a depth of approximately three inches. The accumulation of water jeopardized the structural integrity of the trench, exposing employees to engulfment and cave-in hazards.