Before being taken into use, hoisting machines, fixed gear aboard vessels accessory thereto, and loose gear and wire rope used in connection therewith shall be tested and examined and the safe working load thereof certified in the manner set forth in subpart E of this part.
In the case of untested gear which has been in use, an initial test in conformance with paragraph (a)(1) of this section shall be carried out: Provided, however, That existing standing rigging and wire rope will not be required to be tested but shall be thoroughly examined to ascertain its fitness for continued use in conformance with the requirements of §§ 1919.24 and 1919.25.
If the operation in which cargo gear is engaged never utilizes more than a fraction of the safe working load rating, the owner may, at his option, have said gear certificated for, and limited in operation to, a lesser maximum safe working load: Provided, however, That the gear concerned is physically capable of operation at the original load rating and the load reduction is not for the purpose of avoiding correction of any deficiency.